How can I get environmental clearance certificate?
The project proponent submits an application for environmental clearance with the MoEF if it falls under Project A category or the state government if it falls under project B category. The application form is submitted with EIA report, EMP, details of public hearing and NOC granted by the state regulators.
What is MoEF approval?
In India, MoEF (Ministry of Environment and Forest) is the licensing authority to issue such certification. Necessary packing, labeling, quality, duties and responsibilities are to be maintained by the occupier.
What is the procedure for environmental clearance?
The environmental clearance process comprises of four stages, namely, Stage (1) Screening; Stage (2) Scoping; Stage (3) Public Consultation and Stage (4) Appraisal.
What is EIA clearance?
Environmental Impact Assessment (EIA) is now mandatory under the EPA for 39 categories of developmental activities involving investments of Rs. 50 crores and above. The EIA Notification makes prior Environmental Clearance (EC) compulsory for. All new projects and activities. Expansion/modernization of existing projects.
Which industries require environmental clearance?
(ii)In case of secondary metallurgical processing industrial units, those projects involving operation of furnaces only such as induction and electric arc furnace, submerged arc furnace, and cupola with capacity more than 30,000 tonnes per annum (TPA) would require environmental clearance.
What is the purpose of environmental clearance certificate?
The Environmental Compliance Certificate or ECC refers to the document issued by the DENR-EMB that allows a proposed project to proceed to the next stage of project planning, which is the acquisition of approvals from other government agencies and LGUs, after which the project can start implementation.
Who gives environmental clearance in India?
A nod from the expert panels – the National Board for Wildlife (NBWL), the Forest Advisory Committee (FAC) and 10 Expert Appraisal Committees (EAC) – is necessary for projects to get green clearances from the central government’s Ministry of Environment, Forest and Climate Change (MoEFCC).
What is the first step in EIA?
Screening is the first stage of the EIA process which results in a key EIA decision, namely to either conduct the assessment (based on the likely significant impacts) or not conduct it (in the anticipated absence of such impacts).
What is the validity of environmental clearance?
The validity of prior environmental clearances granted whose validity is expiring in the Financial Year 2020-2021 shall deemed to be extended till the 31st March, 2021 or six months from the date of expiry of validity. The new provision inserted by the amendment reads as follows: “9A.
What are four stages of EIA?
EIA: 7 Steps
- Scoping. Establish the boundaries of the EIA, set the basis of the analyses that will be conducted at each stage, describe the project alternatives and consult the affected public.
- Impact Assessment & Mitigation.
- Impact Management.
- The EIA Report.
- Review & Licensing.
- Monitoring.
WHO issued environmental clearance certificate?
MoEF gives clearance to category A projects and Category B is given clearance by the SEIAA, i.e. State Environment Impact Assessment Authority. Expert Appraisal groups screen the application at the central and the State levels.
What is environmental clearance?